New Smyrna Beach Florida - FDOT project to replace North Causeway hydraulic cylinders begins March 4 limited 7 p m to 7 a m closures expected 26 February 2024 ( news )
New Smyrna Beach , state Florida ( By Press Release office)
Feb 26,2024
| 16| 1
On March 4 , FDOT is set to begin a crucial maintenance project on the North Causeway moveable bridge over the Indian River , also known as the Coronado Beach Bridge , to ensure uninterrupted service and extended functionality for years to come .
The work will involve the removal and replacement of the bridge ' s hydraulic cylinders and the accompanying machinery critical for the operation of the moveable span . These hydraulic cylinders are a vital component that enables the bridge to open and close , allowing marine vessels to pass through the Indian River safely .
It is important to note that , although the contract for this project is scheduled to be initiated on March 4 , there will be no closures at the time of the project ' s commencement . The contractor will begin the project working underneath the bridge and preparing materials in their equipment laydown yard near the structure , which will not disrupt vehicle or marine traffic access . FDOT has taken care to plan the project ' s execution to minimize impacts to the commutes of New Smyrna Beach residents and visitors . Accordingly , the North Causeway will remain open and fully accessible to motorists for the majority of the project’s duration . Marine traffic access will be maintained at all times .
However , given the nature of the work , this project will require limited closures of the North Causeway to vehicle traffic . These closures are strictly confined to a maximum of eight weeknights throughout the entire project , occurring during overnight hours from 7 p . m . to 7 a . m . These closures will not be scheduled on Saturdays , Sundays , major holidays , or during special events . Any necessary overnight closures and/or project updates will be communicated in advance through the FDOT’s Central Florida Roads project webpage at cflroads . com/project/449359 - 1 . Construction schedules are subject to change pending weather or other unforeseen circumstances .
During the brief closure periods , motorists will be redirected to the adjacent South Causeway . Electronic message boards and detour signage will guide drivers around the construction zone to ensure minimal disruption to traffic flow . Please follow posted signage , avoid distractions , and drive cautiously in work zones .
Given the overnight timing and brief nature of the closures , an alternative route for low - speed vehicles , such as golf carts , will not be provided . Please plan your commute accordingly .
The Florida Department of Transportation appreciates the public ' s patience and cooperation as we undertake this necessary maintenance to ensure the continued safe and efficient operation of the North Causeway .
Would you like to know more? Please contact Community Outreach Coordinator Britney Jones at britney . jones@dot . state . fl . us or 386 - 740 - 3566 .