Cedar Rapids City of Five Seasons IO - Edgewood Road Bridge and Trail Improvements 29 February 2024 ( news )
Cedar Rapids City of Five Seasons , state IO ( By Press Release office)
Feb 29,2024
| 9| 1
Edgewood Road Trail Phase 2B is scheduled to begin March 4 , 2024 . This multi - phase project is located on the Edgewood Road bridge between Ellis Road NW and Glass Road NE . Construction will include bridge modifications to accommodate an eight - foot - wide trail with approximately 400 feet of additional trail extending north of the bridge; miscellaneous bridge repairs , additional; and water main replacement and relining , bringing the water main back online after being out of service since 2017 .
Traffic control is planned to remain in place between March 4 and mid - September of this year with lane reductions to northbound and southbound traffic for all stages of work . Two - way traffic will be maintained throughout the duration of construction . Estimated timeline for each stage of work is as follows:
Stage 1: March 4 , 2024 through late June 2024
Stage 2: Late June 2024 through late August 2024
Stage 3: Late August through mid - September 2024
Map of the staged work