Brighton Colorado - Bridge Street widening project update Friday Jan 5 05 January 2024 ( news )
Brighton , state Colorado ( By Press Release office)
Jan 05,2024
| 8| 2
Bridge Street widening project update ( Friday , Jan . 5 ) :
( The following schedule is weather dependent and subject to change )
- Working hours will take place from 7 a . m . to 5 p . m . , Monday through Friday .
- Crews will be working on box culvert extensions and storm sewer and waterline installations on Bridge Street between 22nd Avenue and Sierra Street . Lane shifts are in place within this stretch with a single lane of thru - traffic open in both directions . This traffic reconfiguration is permanent and will remain in effect for the duration of Phase I of the project , which is expected to continue for the next several months .
- For drivers traveling westbound on Bridge Street , there will be no left turns onto 27th Avenue . Drivers are encouraged to continue west to make a lefthand turn at 22nd Avenue .
- Crews will continue to relocate existing power lines and will begin fiber optic relocations within the project zone next week .
- Trucks and heavy equipment will continue to enter and exit the roadway within the project zone , so drivers are encouraged to slow down , watch for workers and equipment , and leave plenty of space in between vehicles . Please be mindful and exercise extreme caution when traveling through construction areas .