American Tobacco District Waterline Replacement – Phase 1 Project Update and Two - Week Look Ahead
May 20 , 2022
The City appreciates your ongoing patience with the work along the busy corridors associated with this project . Additional information regarding this project can be found at:
https://durhamnc . gov/2780/American - Tobacco - District - Waterline - Repl
.
Planned Road / Lane Closures will occur as follows:
Week of 5/23:
Lane closures and shifts in Peabody Street between Main Street and Duke Street .
Lane closures in Jackson Street between Gregson Street and William Vickers Ave , and William Vickers Ave between Jackson Street and Chapel Hill Street .
Week of 5/31:
Lane closures and shifts in Peabody Street between Main Street and Duke Street .
Lane closures in Jackson Street between Gregson Street and William Vickers Ave , and William Vickers Ave between Jackson Street and Chapel Hill Street .
Bicycle Lane and Sidewalk impacts will occur as follows:
Portions of the sidewalk on the west side of Gregson Street between Peabody and Pettigrew streets will have temporary closures to accommodate waterline installation .
Saturday – Sunday May 21 - 22 , 2022:
No work is planned on Saturday or Sunday .
Week of May 23 , 2022:
Peabody Street between Main Street and Duke Street will have local road and lane closures to accommodate waterline installation .
Traffic control signs and markings will be used for the road and lane closures , including at the Gregson / Peabody and Duke / Peabody intersections .
Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations .
Peabody Street between Main Street and Gregson Street will have isolated closures with local access being maintained .
Pavement along Peabody Street will be rough and uneven as final pavement repairs are being completed .
Noise levels in excess of the current City noise ordinance are anticipated during work hours .
Planned work hours are 7 AM to 7 PM .
No water or sewer service disruptions are anticipated .
Jackson Street between Gregson Street and William Vickers Ave , and William Vickers Ave between Jackson Street and Chapel Hill Street will have lane closures and traffic shifts to accommodate waterline installation , pavement restoration , and sanitary sewer rehabilitation .
Traffic control signs and markings will be used for the lane closures and shifts . Northbound traffic on William Vickers Ave will be maintained .
Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations .
Pavement along Jackson St and William Vickers Ave will be rough and uneven as final pavement repairs are being completed .
Noise levels in excess of the current City noise ordinance are anticipated during work hours .
Planned work hours are 7 AM to 7 PM .
No water or sewer service disruptions are anticipated .
Saturday , Sunday , and Monday May 28 - 30 , 2022:
No work is planned on Saturday , Sunday , or Monday ( Memorial Day ) .
Week of May 31 , 2022:
Peabody Street between Main Street and Duke Street will have local road and lane closures to accommodate waterline installation .
Traffic control signs and markings will be used for the road and lane closures , including at the Gregson / Peabody and Duke / Peabody intersections .
Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations .
Peabody Street between Main Street and Gregson Street will have isolated closures with local access being maintained .
Pavement along Peabody Street will be rough and uneven as final pavement repairs are being completed .
Noise levels in excess of the current City noise ordinance are anticipated during work hours .
Planned work hours are 7 AM to 7 PM .
No water or sewer service disruptions are anticipated .
Jackson Street between Gregson Street and William Vickers Ave , and William Vickers Ave between Jackson Street and Chapel Hill Street will have lane closures and traffic shifts to accommodate waterline installation and pavement restoration .
Traffic control signs and markings will be used for the lane closures and shifts . Northbound traffic on William Vickers Ave will be maintained .
Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations .
Pavement along Jackson St and William Vickers Ave will be rough and uneven as final pavement repairs are being completed .
Noise levels in excess of the current City noise ordinance are anticipated during work hours .
Planned work hours are 7 AM to 7 PM .
No water or sewer service disruptions are anticipated .
Saturday – Sunday June 4 - 5 , 2022:
No work is planned on Saturday or Sunday .
If you have questions , please email
Lisa . Mitchell@durhamnc . gov
.

PLAY the NEWS
* May be useful for visually impaired persons .
Press release information :
Direct link to press release:
Click here .