Local news- Press Release
Watertown Connecticut - Guernseytown Road Reconstruction 12 February 2024 ( news )
Watertown , state Connecticut ( By Press Release office)
Feb 12,2024
| 12| 1
PRESS RELEASE
FOR IMMEDIATE RELEASE
Watertown , CT – February 9 , 2024
Guernseytown Road is currently being reconstructed utilizing a 100% State Grant .
Work Starting Next Week
Additional drainage work will be placed under Guernseytown Road from Monday February 12
thto Wednesday February 14
th
, 2024 . A portion of the road will be one lane with traffic control officers to alternate the traffic . You may also seek alternate routes to avoid this area .
Work Starting at the End of February 2024
To enhance the environmental quality of Watertown Streams and Rivers a large Hydrodynamic Separator is scheduled to be installed on this project . To install this on Guernseytown Road it is anticipated that the road will be closed from Thursday February 29th , 2024 , until March 28th , 2024 .
All residents will have access to their homes . The specific location of the road closure is as follows; closed north of West Road at 629 Guernseytown and south of Crestview Dr at 641 Guernseytown Road . Residents 629 and below will need to go south to get to Route 6 and residents 641 and above will need to utilize Platt Road to get to Route 6 .
It is anticipated that this work will require blasting of ledge rock and a specialized large manhole that will need to be installed with a crane at this location .
Thank you for your understanding .
PLAY the NEWS
* May be useful for visually impaired persons .
Press release information :
Direct link to press release:
Click here .